Demolition of existing single storey garage and utility room to side, erection of two storey side/rear extension, lower ground garage, two storey front extension and changes to fenestration

📊

See the success rate & inspector analytics

Free to view — just create an account, no payment needed.

Sign Up Free

Technical Issues Heatmap

Trees & Landscape
Extensions

Inspector’s Reasoning

Appeal Decision Site visit made on 28 July 2026 by A Wright BSc (Hons) MRTPI an Inspector appointed by the Secretary of State Decision date: 5 August 2026 Appeal Ref: 6011791 4 Wynnstow Park, Oxted, Surrey RH8 9DR  The appeal is made under section 78 of the Town and Country Planning Act 1990 (as amended) against a refusal to grant approval to details required by conditions of a planning permission.  The appeal is made by Helen Peck against the decision of Tandridge District Council.  The application Ref TA/2024/1240/Cond1 sought approval of details pursuant to conditions Nos 3 and 4 of a planning permission Ref TA/2024/1240, granted on 31 January 2025.  The application was refused by notice dated 8 May 2026.  The development proposed is demolition of existing single storey garage and utility room to side, erection of two storey side/rear extension, lower ground garage, two storey front extension and changes to fenestration.  The details for which approval is sought are the tree protection plan and arboricultural method statement and method statement for the demolition and/or construction of the development. Decision 1. The appeal is dismissed. Background and Main Issues 2. Planning permission was granted by the Council in January 20251 for the demolition of the garage and utility room and erection of extensions, a garage and changes to the fenestration. 3. Condition 3 of the original approval states that: ‘Notwithstanding the details already submitted, no development shall start until a detailed tree protection plan and detailed arboricultural method statement, in full accordance with sections 5.5 and 6.1 of BS5837:2012 Trees in relation to design, demolition and construction - Recommendations [appropriate and specific to the approved scheme], to include details of all works within the root protection area, or crown spread [whichever is greater], of any retained tree, and all site set up and tree protection measures to be employed has been submitted to and agreed in writing by the Local Planning Authority. Thereafter, all works shall be carried out and constructed in accordance with the approved details and shall not be varied without the written consent of the Local Planning Authority.’ 4. Condition 3 was imposed ‘In the interests of ensuring the suitable protection of trees at the site, in accordance with Policy DP7 of the Tandridge District Local Plan Part 2: Detailed Policies 2014 and Policy CSP18 of the Tandridge District Core Strategy 2008’. 5. Condition 4 of the original approval states that: ‘No development shall take place before a method statement for the demolition and/or construction of the 1 Application ref TA/2024/1240, the ‘original approval’ Appeal Decision 6011791 2 development hereby approved has been submitted to, and approved in writing by, the Local Planning Authority. The demolition and construction works shall be carried out in accordance with the approved method statement. Details submitted in respect of the method statement, incorporated on a plan, shall provide for details of the provision of parking facilities for contractors during all stages of the development (excavation, site preparation and construction) and the provision of a means of storage and/or delivery for all plant, site huts, site facilities and materials. It should also include a risk assessment of the potentially damaging construction activities’. 6. Condition 4 was imposed ‘In the interests of neighbour amenity and ensuring the suitable protection of trees at the site, in accordance with Policy DP7 of the Tandridge District Local Plan Part 2: Detailed Policies 2014 and Policy CSP18 of the Tandridge District Core Strategy 2008’. 7. The appellant sought approval for the tree protection plan, arboricultural method statement, and demolition and construction method statement to meet the requirements of conditions 3 and 4. This was refused by the Council as it considered that insufficient information had been submitted to meet the requirements of the conditions. 8. Therefore, the main issues are whether:  the tree protection plan and arboricultural method statement meet the requirements of condition 3; and  the demolition and construction method statement meets the requirements of condition 4. Reasons Tree protection plan and arboricultural method statement 9. The appeal site comprises a dwelling with a side garage, beside which are several trees including mature beech trees in good condition. The appellant has submitted an additional Arboricultural Method Statement (AMS) in relation to condition 3 to be read in conjunction with the original AMS which formed part of the planning application documents. Both include the same tree protection plan (TPP) showing root protection areas (RPAs) for the trees on and adjacent to the site which are used to inform the construction exclusion, ground protection and precautionary zones (the tree protection zones) and the management of activities within them. 10. BS5837:2012 Trees in relation to design, demolition and construction – Recommendations (BS5837) indicates that the RPA for each tree should initially be plotted as a circle centred on the base of the stem. Where pre-existing site conditions or other factors indicate that rooting has occurred asymmetrically, it states that a polygon of equivalent area should be produced. Modifications to the shape of the RPA should reflect a soundly based arboricultural assessment of likely root distribution. 11. BS5837 outlines several factors which should be taken into account in any deviation in the RPA from the original circular plot. This includes the morphology and disposition of the roots, when influenced by past or existing site conditions (e.g. the presence of structures). Appeal Decision 6011791 3 12. The TPP shows circular RPAs for the trees beside the existing building. This includes tree T1, a high-quality beech tree protected by a Tree Preservation Order whose RPA extends under the garage. The Council states that as there are no tree roots under the garage, the RPA should not be plotted within the footprint of this building but should extend out into other unconstrained areas. 13. The TPP shows a dashed purple line indicating an amended RPA to reflect site conditions. The original AMS indicates that the RPA for this tree is offset due to hard landscape and a retaining wall to the south. However, the amended RPA does not appear to reflect the position of tree T1, particularly on the south side of the tree. Further, there appears to be no soundly based justification for the modified RPA as required by BS5837. This could have consequent implications for the extent of the tree protection zones and location of the tree protective fencing. 14. Policy CSP18 of the Tandridge District Core Strategy 2008 (CS) and Policy DP7 of the Tandridge Local Plan Part 2 Detailed Policies 2014 (LPDP) require proposals to respect the character and local context, including retaining existing important features such as trees, amongst other things. In the absence of a clear and soundly based amended RPA for the protected beech tree T1, I cannot be satisfied that this tree would be adequately protected. As such, I find conflict with Policies CSP18 and DP7. 15. Consequently, I conclude that the submitted TPP and AMS fail to meet the requirements of condition 3. Method statement for demolition and/or construction of the approved development 16. The Council finds much of the information in the appellant’s Demolition and Construction Method Statement (DCMS) acceptable. Nevertheless, whilst the DCMS states that contractor and operative parking shall be provided within the site boundary as shown on the site logistics/setup plan, this plan only indicates the areas where construction materials would be unloaded. It does not outline details of the parking facilities for contractors as required by condition 4. 17. Further, section 6.2 of the additional AMS lists activities which are strictly prohibited within the RPAs and fenced construction exclusion zones (CEZ), including storage of materials, spoil or plant. However, when read in conjunction with the TPP, the site logistics/setup plan in the DCMS indicates that construction materials would be unloaded within part of the CEZ. Unloading means that there would be at least some temporary storage of materials in this location, so there is a conflict between the submitted DCMS and the TPP. 18. As set out above, Policies CSP18 of the CS and Policy DP7 of the LPDP require important features such as trees to be retained. Without clarity of where contractors would park and that materials would not be unloaded nor stored even temporarily within the CEZ, I cannot be certain that construction activities associated with the original approval would not harm trees. Thus, the submitted DCMS is contrary to Policies CSP18 and DP7. 19. Therefore, I conclude that the submitted DCMS does not meet the requirements of condition 4. Appeal Decision 6011791 4 Other Matters 20. The appellant has expressed dissatisfaction with the Council’s handling of the application given that they tried to engage with the Council to address the issues and including the length of time taken to reach a decision on it. Nonetheless, this is a matter between those parties and does not in this instance have any bearing on my determination of this appeal. Conclusion 21. For the reasons given above, the appeal should be dismissed. A Wright INSPECTOR
Expert Representation

Don't leave your appeal to chance.

Inspectors are inconsistent. We build a technical defense using precedents from our 182,000+ case archive.
No win, no fee Householder representation — you only pay if you win.

Get Free Review How it works →