Installation of a Battery Energy Storage Facility, substation, underground cabling, access, landscaping and ancillary infrastructure & equipment to include water tower, security fence, acoustic fence & gates
📊
Borough Success Rate
In Walsall Metropolitan Borough Council, approx 50.0% of Other Major Developments appeals are successful. (Sample: 4 cases).
Planzo Professional Representation
Technical Appeal Representation
This Other Major Developments case requires a bespoke technical strategy. Contact us for a fixed-fee quotation.
Technical Issues Heatmap
Instant scan of technical battlegrounds available with a Day Pass.
Inspector Profile: Gethin T
Archive Data: 9 Decisions
Allowance Rate (Other Major Developments)
88.9%
↑ High
National Average (Other Major Developments)
43.4%
Inspector's Analysis
https://www.gov.uk/planning-inspectorate
Appeal Decision
Site visit made on 16 March 2026
by T Gethin BA (Hons), MSc, MRTPI
an Inspector appointed by the Secretary of State
Decision date: 31 March 2026
Appeal Ref: 6001998
Land at Six Towers Road, Walsall WS2 8XA
• The appeal is made under section 78 of the Town and Country Planning Act 1990 (as amended)
against a refusal to gra…