Demolition of Redundant Industrial Building, Dwelling and Small-Scale Mixed Business Units and Construction of 13 no. Mixed Use Business Units Including 1 no. Live/Work Unit
📊
Borough Success Rate
In Cornwall Council, approx 37.2% of Other Major Developments appeals are successful. (Sample: 43 cases).
Planzo Professional Representation
Technical Appeal Representation
This Other Major Developments case requires a bespoke technical strategy. Contact us for a fixed-fee quotation.
Technical Issues Heatmap
Instant scan of technical battlegrounds available with a Day Pass.
Inspector Profile: Spencer-Peet A
Archive Data: 4 Decisions
Allowance Rate (Other Major Developments)
25.0%
↓ Strict
National Average (Other Major Developments)
43.4%
Inspector's Analysis
https://www.gov.uk/planning-inspectorate
Appeal Decision
Site visit made on 16 July 2024
by Mr A Spencer-Peet BSc(Hons) PGDip.LP Solicitor (Non Practising)
an Inspector appointed by the Secretary of State
Decision date: 27 August 2024
Appeal Ref: APP/D0840/W/23/3333661
Viaduct Works, Frog Hill, Ponsanooth, Cornwall, TR3 7JW
• The appeal is made under section 78 of the Town and …