Installation of a solar farm comprising ground mounted solar PV panels with a generating capacity of up to 49.99MW(AC), including mounting framework, inverters, underground cabling, stock proof fence, CCTV, internal tracks and associated infrastructure, landscaping and ecological works for a temporary period of 50 years
📊
Borough Success Rate
In North Kesteven District Council, approx 28.6% of Other Major Developments appeals are successful. (Sample: 7 cases).
Planzo Professional Representation
Technical Appeal Representation
This Other Major Developments case requires a bespoke technical strategy. Contact us for a fixed-fee quotation.
Technical Issues Heatmap
Instant scan of technical battlegrounds available with a Day Pass.
Inspector Profile: Chamberlain G
Archive Data: 7 Decisions
Allowance Rate (Other Major Developments)
28.6%
↓ Strict
National Average (Other Major Developments)
43.4%
Inspector's Analysis
https://www.gov.uk/planning-inspectorate
Appeal Decision
Site visit made on 3 February 2026
by Graham Chamberlain BA (Hons) MSc MRTPI
an Inspector appointed by the Secretary of State
Decision date: 16th February 2026
Appeal Ref: APP/R2520/W/25/3373351
Land to the east and west of Mareham Lane, Sleaford, North Kesteven,
Lincolnshire NG34 0AW
The appeal is made under section 7…