Demolition of the existing former youth centre and erection of 49 Retirement Living apartments with associated communal facilities, vehicular access, car parking and landscaping. Provision of a new multi-use games area and children's play area to the southwest of the existing former youth centre
📊
Borough Success Rate
In Dudley Metropolitan Borough Council, approx 50.0% of Major dwellings appeals are successful. (Sample: 6 cases).
Planzo Professional Representation
Technical Appeal Representation
This Major dwellings case requires a bespoke technical strategy. Contact us for a fixed-fee quotation.
Technical Issues Heatmap
Instant scan of technical battlegrounds available with a Day Pass.
Inspector Profile: Aston R
Archive Data: 41 Decisions
Allowance Rate (Major dwellings)
24.4%
↓ Strict
National Average (Major dwellings)
41.1%
Inspector's Analysis
https://www.gov.uk/planning-inspectorate
Appeal Decision
Inquiry held on 14 to 16 October 2025 and 24 to 25 November 2025
Site visits made on 13, 14 and 16 October and 24 November 2025
by R Aston BSc (Hons) DipTP MRTPI
an Inspector appointed by the Secretary of State
Decision date: 27 March 2026
Appeal Ref: APP/C4615/W/25/3368014
Former Kingswinford Youth Centre, High Street, King…