Construction and operation of a solar farm and battery energy storage system, together with all associated works, equipment, necessary infrastructure and landscaping
📊
Borough Success Rate
In Bassetlaw District Council, approx 75.0% of Other Major Developments appeals are successful. (Sample: 4 cases).
Planzo Professional Representation
Technical Appeal Representation
This Other Major Developments case requires a bespoke technical strategy. Contact us for a fixed-fee quotation.
Technical Issues Heatmap
Instant scan of technical battlegrounds available with a Day Pass.
Inspector Profile: Heward H
Archive Data: 5 Decisions
Allowance Rate (Other Major Developments)
40.0%
↓ Strict
National Average (Other Major Developments)
43.4%
Inspector's Analysis
https://www.gov.uk/planning-inspectorate
Appeal Decision
Inquiry held 20 and 21 January 2026
Site visits made 17 and 19 January 2026
by Helen Heward BSc (Hons) MRTPI
an Inspector appointed by the Secretary of State
Decision date: 7th April 2026
Appeal Ref: APP/A3010/W/25/3367817
Land adjacent to the A614, Worksop, S80 3PA
The appeal is made under section 78 of the Town and Co…