Construction and operation of the Swadlincote Resource Recovery Park (SRRP) comprising an Energy Recovery Facility (ERF) and Aggregate Recovery Facility (ARF) together with ancillary infrastructure including grid connection cable and works, private electrical wire provision, substation, CHP off-take provision, internal vehicle circulation and yard areas, weighbridges, car parking, new access road, temporary construction compound and laydown areas, security fencing and gates, drainage, landscaping and off-site habitat compensation and biodiversity
📊
Borough Success Rate
In Derbyshire County Council, approx 100.0% of Other Major Developments appeals are successful. (Sample: 1 cases).
Planzo Professional Representation
Technical Appeal Representation
This Other Major Developments case requires a bespoke technical strategy. Contact us for a fixed-fee quotation.
Technical Issues Heatmap
Instant scan of technical battlegrounds available with a Day Pass.
Inspector Profile: Griffiths P
Archive Data: 14 Decisions
Allowance Rate (Other Major Developments)
64.3%
↑ High
National Average (Other Major Developments)
43.4%
Inspector's Analysis
https://www.gov.uk/planning-inspectorate
Appeal Decision
Inquiry opened on 23 April 2025
by Paul Griffiths BSc(Hons) BArch IHBC
an Inspector appointed by the Secretary of State
Decision date: 4th August 2025
Appeal Ref: APP/U1050/W/24/3354670
Land adjacent to Willshees Depot 3, Keith Willshee Way, Swadlincote DE11 9EN
• The appeal is made under section 78 of the Town and Country…