Installation of a solar farm comprising ground mounted solar PV panels with a generating capacity of up to 49.99MW, including mounting system, inverters, underground cabling, stock proof fence, CCTV, internal tracks and associated infrastructure, landscaping, biodiversity net gain and environmental enhancements, for a temporary period of 50 years
📊
Borough Success Rate
In North Northamptonshire, approx 0.0% of Other Major Developments appeals are successful. (Sample: 2 cases).
Planzo Professional Representation
Technical Appeal Representation
This Other Major Developments case requires a bespoke technical strategy. Contact us for a fixed-fee quotation.
Technical Issues Heatmap
Instant scan of technical battlegrounds available with a Day Pass.
Inspector Profile: Major P
Archive Data: 7 Decisions
Allowance Rate (Other Major Developments)
85.7%
↑ High
National Average (Other Major Developments)
43.4%
Inspector's Analysis
https://www.gov.uk/planning-inspectorate
Appeal Decision
Hearing Held on 20 May 2025
Site visit made on 21 May 2025
by Philip Major BA(Hons) DipTP MRTPI
an Inspector appointed by the Secretary of State for Housing Communities and Local Government
Decision date: 14th July 2025
Appeal Ref: APP/M2840/W/24/3354297
Land south of Wood Lodge Farm, Thrapston
• The appeal is made under sect…