Installation of a solar farm comprising ground mounted solar panels; access tracks; inverter/transformers; substation; storage, spare parts and welfare cabins; underground cables and conduits; perimeter fence; CCTV equipment; temporary construction compounds; and associated infrastructure and planting scheme
📊
Borough Success Rate
In Ashford Borough Council, approx 16.7% of Other Major Developments appeals are successful. (Sample: 6 cases).
Planzo Professional Representation
Technical Appeal Representation
This Other Major Developments case requires a bespoke technical strategy. Contact us for a fixed-fee quotation.
Technical Issues Heatmap
Instant scan of technical battlegrounds available with a Day Pass.
Inspector Profile: Griffiths P
Archive Data: 14 Decisions
Allowance Rate (Other Major Developments)
64.3%
↑ High
National Average (Other Major Developments)
43.4%
Inspector's Analysis
https://www.gov.uk/planning-inspectorate
Appeal Decision
Inquiry opened on 4 February 2025
Site visits made on 12 February 2025 and 5 March 2025
by Paul Griffiths BSc(Hons) BArch IHBC
an Inspector appointed by the Secretary of State
Decision date: 8th July 2025
Appeal Ref: APP/E2205/W/24/3352427
Land south of the M20, Church Lane, Aldington, Kent
• The appeal is made under secti…