Construction, operation and subsequent decommissioning of a renewable energy park comprising ground mounted Solar Photovoltaics (PV) with co-located Battery Energy Storage System (BESS) at the point of connection, together with associated infrastructure, access, landscaping and cabling
📊
Borough Success Rate
In Warwick District Council, approx 36.4% of Other Major Developments appeals are successful. (Sample: 11 cases).
Planzo Professional Representation
Technical Appeal Representation
This Other Major Developments case requires a bespoke technical strategy. Contact us for a fixed-fee quotation.
Technical Issues Heatmap
Instant scan of technical battlegrounds available with a Day Pass.
Inspector Profile: Major P
Archive Data: 7 Decisions
Allowance Rate (Other Major Developments)
85.7%
↑ High
National Average (Other Major Developments)
43.4%
Inspector's Analysis
https://www.gov.uk/planning-inspectorate
Appeal Decisions
Hearing Held on 14 January 2025
Site visits made on 13 and 14 January 2025
by Philip Major BA(Hons) DipTP MRTPI
an Inspector appointed by the Secretary of State for Housing, Communities and Local Government
Decision date: 30 January 2025
Appeal Ref: APP/T3725/W/24/3347315
Land to the south of Birmingham Road, Kenilworth
• Th…