Breach of planning control as alleged in the notice is, without planning permission, the material change of use of a caravan site approved by an exempted organisation under the provisions of The Caravan Sites and Control of Development Act 1960 to a mixed use for storage of two steel containers and building materials and a permanent recreational camping and caravan site with the additional associated infrastructure namely shower and toilet blocks, electric hook ups, fire assembly points and two tents
📊
Borough Success Rate
In King's Lynn and West Norfolk Borough Council, approx 31.5% of Change of use appeals are successful. (Sample: 73 cases).
Planzo Professional Representation
Technical Appeal Representation
This Change of use case requires a bespoke technical strategy. Contact us for a fixed-fee quotation.
Technical Issues Heatmap
Instant scan of technical battlegrounds available with a Day Pass.
Inspector Profile: Freer P
Archive Data: 21 Decisions
Allowance Rate (Change of use)
19.0%
↓ Strict
National Average (Change of use)
32.5%
Inspector's Analysis
https://www.gov.uk/planning-inspectorate
Appeal Decision
Hearing Held on 16 March 2021 and 20 April 2021
Site visit made on 22 June 2021
by Paul Freer BA (Hons) LLM PhD MRTPI
an Inspector appointed by the Secretary of State
Decision date: 27 August 2021
Appeal Ref: APP/V2635/C/18/3216570
Land South of 38 to 42 Main Road, Holme-next-the-Sea, Norfolk
• The appeal is made under sect…