Site visit made on 12 September 2018
by D J Barnes MBA BSc(Hons) DipTP MRTPI
an Inspector appointed by the Secretary of State
Decision date: 2nd October 2018
Appeal Ref: APP/T0355/D/18/3207923
1 White Rock, Ray Mill Road East, Maidenhead SL6 8UD
The appeal is made under section 78 of the Town and Country Planning Act 1990
against a refusal to grant planning permission.
The appeal is made by Mr and Mrs Neal Shipman against the decision of the Council of
the Royal Borough of Windsor and Maidenhead.
The application Ref 18/01223, dated 17 April 2018, was refused by notice dated
20 June 2018.
The development proposed is the erection of a ground floor side/rear extension and
alterations to existing fenestration.
Decision
1. The appeal is dismissed.
Procedural Matter
2. Since the appeal was lodged the revised National Planning Policy Framework
has been published but does not raise any additional matters.
Main Issue
3. It is considered that the main issue is the effect of the proposed development
on the risk of flooding.
Reasons
4. The Council’s objection to the proposed erection of a single storey extension is
solely related to the host property being located within Flood Zone 3 and the
absence of any flood risk assessment to determine whether there would be the
potential to exacerbate flooding. Policy F1 of the Royal Borough of Windsor
and Maidenhead Local Plan (incorporating Alterations) (LP) and the
accompanying Supplementary Planning Guidance: Interpretation of Policy F1
(Development within Areas Liable to Flood) (SPG) identify the circumstances
when for minor development, such as extensions, there is a need for a flood
risk assessment and any mitigation measures to be submitted. The threshold
for a flood risk assessment is an extension which individually, or cumulatively
with other alterations, would result in an increase at ground floor level of
30sq m.
5. The drafting of this policy and the SPG precedes the Planning Practice Guidance
which includes reference to the application of the Environment Agency’s
standing advice for minor development within floodplains. For schemes within
Flood Zone 3 a flood risk assessment is required. Although drafted before the
Appeal Decision APP/T0355/D/18/3207923
2
publication of the Planning Practice Guidance, LP Policy F1 and the SPG are
generally consistent with the national guidance.
6. The pre-application advice provided to the appellants by the Council for a
previous application for a similar form of development (Ref 18/00240) did not
identify that the site of the proposed extension was within a floodplain.
However, evidence has been provided to demonstrate that the property is
within Flood Zone 3. In the absence of any flood risk assessment there is
limited information available to determine whether the appeal scheme would
have an adverse effect on the floodplain or impede the flow of flood water.
Further, no flood resilience measures are included on the submitted drawings.
7. Reference has been made by the appellants to the consideration by the Council
of a residential scheme at Boulters Meadow and the potential for the adjacent
water body to mitigate potential flooding. The submission of a flood risk
assessment for Boulters Meadow reflects the requirements of LP Policy F1 and
the SPG. Whether the water body would provide suitable flood mitigation for
the property has not been demonstrated by any specific evidence. For these
reasons, only limited weight has been given to these matters in the
determination of this appeal.
8. Accordingly, and having regard to all other matters, it is concluded that this
appeal should be dismissed because, in the absence of a flood risk assessment,
the proposed development has the potential to result in an unacceptable risk of
flooding and, as such, it would conflict with LP Policy F1, the SPG and the
Planning Practice Guidance.
D J Barnes
INSPECTOR
£
Costs decision section
Costs Decision
Site visit made on 12 September 2018
by D J Barnes MBA BSc(Hons) DipTP MRTPI
an Inspector appointed by the Secretary of State
Decision date: 2nd October 2018.
Costs application in relation to Appeal Ref: APP/T0355/D/18/3207923
1 White Rock, Ray Mill Road East, Maidenhead SL6 8UD
The application is made under the Town and Country Planning Act 1990, sections 78,
322 and Schedule 6, and the Local Government Act 1972, section 250(5).
The application is made by Mr and Mrs Neal Shipman for a full award of costs against
the Council of the Royal Borough of Windsor and Maidenhead.
The appeal was against the refusal of planning permission for the erection of a ground
floor side/rear extension and alterations to existing fenestration.
Decision
1. The application for an award of costs is refused.
Reasons
2. The Planning Practice Guidance advises that costs may be awarded against a
party who has behaved unreasonably and thereby caused the party applying
for costs to incur unnecessary or wasted expense in the appeal process.
3. The appellants are applying for a full award of costs because the Council should
not have refused planning permission because it conflicted with the pre-
application advice regarding the appeal property not being within a floodplain.
Further, the Council has not sought solutions to address the flooding issues and
has acted unreasonably in how the application was assessed.
4. The Council refutes the claim about unreasonable behaviour and identifies that
the appeal application was not specifically the subject of pre-application advice.
This advice was related to a previous application that was withdrawn prior to
determination (Ref 18/00240). During the application process the appellants
did not contact the Planning Officer to discuss matters and the application was
refused because it was contrary to policy.
5. Although why the original pre-application advice was incorrect has not been
explained, there is clear evidence that the appeal site is within Flood Zone 3.
There are requirements in the Planning Practice Guidance and development
plan to provide a flood risk assessment for minor developments, such as the
proposed extension. The absence of the required flood risk assessment formed
the basis of the reason for refusing the application and, for this reason, the
Council did not act unreasonably. Whether better communication between the
Council and the appellants about the need for a flood risk assessment and if
such an assessment was submitted this might have avoided the refusal of
planning permission would be unfounded speculation in the absence of such
information.
Costs Decision APP/T0355/D/18/3207923
2
6. I therefore find that unreasonable behaviour resulting in unnecessary or
wasted expense, as described in the Planning Practice Guidance, has not been
demonstrated and that a full award of costs is not justified.
D J Barnes
INSPECTOR
Expert Representation
Don't leave your appeal to chance.
Inspectors are inconsistent. We build a technical defense using precedents from our 182,000+ case archive.
No win, no fee Householder representation — you only pay if you win.