Site visit made on 31 October 2022
by B Phillips BSc MSc MRTPI
an Inspector appointed by the Secretary of State
Decision date: 11th November 2022
Appeal Ref: APP/Z5630/D/22/3296507
6 Gordon Road, Kingston Upon Thames KT2 6BS
• The appeal is made under section 78 of the Town and Country Planning Act 1990
against a refusal to grant approval required under Schedule 2, Part 1, Class A,
Paragraph A.4 of the Town and Country Planning (General Permitted Development)
(England) Order 2015 (as amended).
• The appeal is made by Mr J Harkins against the decision of the
Council of the Royal Borough of Kingston Upon Thames.
• The application Ref 22/00340/PAEXT, dated 26 January 2022, was refused by notice
dated 18 March 2022.
• The development proposed is the erection of a rear single storey extension that will
extend beyond the original back wall of the dwelling by approx. 7.5m with a maximum
height of approx. 3 metres
Decision
1. The appeal is dismissed.
Preliminary Matters
2. It should be noted that the submitted site location plan and block plan identify
No 8 Gordon Road, not No 6. Given that the appeal is dismissed, it is not
necessary for me to address this issue further.
3. Under Article 3(1) and Schedule 2, Part 1, Class A of the Town and Country
Planning (General Permitted Development) (England) Order 2015 as amended
(the GPDO), planning permission is granted for the enlargement of a
dwellinghouse subject to limitations and conditions.
Main Issue
4. I consider that the main issues in this appeal are whether the proposed
development would be granted planning permission by Article 3, Schedule 2,
Part 1, Class A of the GPDO.
Reasons
5. Paragraph A.4 (10) of Article 3(1) and Schedule 2, Part 1, Class A of the GDPO
sets out the following:
The development must not begin before the occurrence of one of the
following—
(a)the receipt by the developer from the local planning authority of a written
notice that their prior approval is not required;
Appeal Decision APP/Z5630/D/22/3296507
2
(b)the receipt by the developer from the local planning authority of a written
notice giving their prior approval; or
(c)the expiry of 42 days following the date on which the information referred to
in sub-paragraph (2) was received by the local planning authority without the
local planning authority notifying the developer as to whether prior approval is
given or refused.
6. On my site visit I observed that the extension applied for under this prior
approval application appears to have been constructed. The appellant has
confirmed that this is the case.
7. For the above reason, I conclude that the extension would not accord with
limitation A.4 (10) of Class A. Consequently, the proposal would not comply
with the conditions, limitations, and restrictions applicable to development
permitted under Part 1, Class A, Schedule 2 of the GPDO. Therefore, the
development does not constitute permitted development under Class A.
8. As I have reached this conclusion, it is not necessary for me to consider
whether the proposal would be acceptable with regards to the other criteria and
limitations of Class A.
Conclusion
9. For the reasons given, and having regard to all other matters raised, the
appeal is dismissed.
B Phillips
INSPECTOR
Expert Representation
Don't leave your appeal to chance.
Inspectors are inconsistent. We build a technical defense using precedents from our 182,000+ case archive.
No win, no fee Householder representation — you only pay if you win.