Construction of two holiday units
📊
Borough Success Rate
In Cornwall Council, approx 37.2% of Other Major Developments appeals are successful. (Sample: 43 cases).
Planzo Professional Representation
Technical Appeal Representation
This Other Major Developments case requires a bespoke technical strategy. Contact us for a fixed-fee quotation.
Technical Issues Heatmap
Instant scan of technical battlegrounds available with a Day Pass.
Inspector Profile: Cresswell C
Archive Data: 4 Decisions
Allowance Rate (Other Major Developments)
50.0%
↑ High
National Average (Other Major Developments)
43.4%
Inspector's Analysis
https://www.gov.uk/planning-inspectorate
Appeal Decision
Site visit made on 21 September 2021
by Colin Cresswell BSc (Hons) MA MBA MRTPI
an Inspector appointed by the Secretary of State for Communities and Local Government
Decision date: 27 October 2021
Appeal Ref: APP/D0840/W/21/3277598
Sennen Rise, Mayon Farm, Sennen TR19 7AD
• The appeal is made under section 78 of the Town and …