Construction of a solar park, to include the installation of solar photovoltaic panels to generate approximately 35 MW of electricity, with DNO and Client substations, inverters, perimeter stock fencing, access tracks and CCTV. Landscaping and other associated works
📊
Borough Success Rate
In Hinckley and Bosworth Borough Council, approx 25.0% of Other Major Developments appeals are successful. (Sample: 4 cases).
Planzo Professional Representation
Technical Appeal Representation
This Other Major Developments case requires a bespoke technical strategy. Contact us for a fixed-fee quotation.
Technical Issues Heatmap
Instant scan of technical battlegrounds available with a Day Pass.
Inspector Profile: Parker C
Archive Data: 14 Decisions
Allowance Rate (Other Major Developments)
78.6%
↑ High
National Average (Other Major Developments)
43.4%
Inspector's Analysis
https://www.gov.uk/planning-inspectorate
Appeal Decision
Virtual Hearing Held on 20 & 22 April 2021
Unaccompanied Site Visits made on 19 April & 21 April 2021
by Cullum J A Parker BA(Hons) MA MRTPI MCMI IHBC
an Inspector appointed by the Secretary of State for Housing, Communities and Local Government
Decision date: 4 May 2021
Appeal Ref: APP/K2420/W/21/3266505
Hangmans Hall …