Appeal Decision
Site visit made on 9 November 2020
by E Brownless BA (Hons) Solicitor (non-practising)
an Inspector appointed by the Secretary of State
Decision date: Wednesday, 17 March 2021
Appeal Ref: APP/N1920/D/20/3255407
5 Field View Road, Potters Bar EN6 2LY
• The appeal is made under section 78 of the Town and Country Planning Act 1990
against a refusal to grant planning permission.
• The appeal is made by Abbey Hope-Evans against the decision of Hertsmere Borough
Council.
• The application Ref: 20/0451/HSE, dated 27 March 2020, was refused by notice dated
29 May 2020.
• The development proposed is described as ‘retrospective construction and use of an
outbuilding for a home business ancillary to the use of the dwellinghouse’.
Decision
1. The appeal is dismissed.
Procedural Matters
2. At the time of my site visit I observed that the outbuilding had been
constructed and I have therefore considered the appeal scheme before me on
this basis.
3. I have considered the appeal before me on the basis of the operating hours
that were originally applied for. I have then gone on to consider whether
reducing the daily number of classes would make the scheme acceptable. This
alternative operating arrangement formed part of the original application and
therefore I am satisfied that relevant parties have had the opportunity to
consider this option and comment accordingly. As part of the appeal, further
alternative operating arrangements have been put forward by the appellant.
These include individual attendance at each class, reduced hours of operation
on a Friday, no hours of operation on a Friday, a maximum of 5 clients per day
or 15 clients per week. It is not clear on the information before me that
interested parties views have been sought on these and therefore I cannot be
satisfied that no party would be prejudiced by my consideration of these
matters. Moreover, there are limited details before me on how the suggested
alternatives might operate and whether alone or in combination.
Consequently, I have determined the appeal on the basis of the scheme and
plans that were before the local planning authority when it made its decision.
Application for costs
4. An application for costs was made by Abbey Hope-Evans against Hertsmere
Borough Council. This application is the subject of a separate Decision.
Appeal Decision APP/N1920/D/20/3255407
2
Main Issues
5. The main issues are the effect of the proposed development on the character
and appearance of the surrounding area and the living conditions of the
occupiers of neighbouring dwellings with particular regard to noise and
disturbance.
Reasons
Character and appearance
6. No 5 Field View Road comprises a semi-detached dwelling with hardstanding to
its front that can accommodate three parked cars. To its rear is a modest sized
private garden with a single storey flat roof outbuilding (the studio) constructed
in the rearmost part of the garden. It broadly fills the full width of the plot. The
internal space is mainly open plan, but there is a smaller separate storage
room positioned forward of the main front build line. The building has been in
use for pilates classes although it is not given over to the exclusive use of the
business. It is also used by the appellant for her own enjoyment and personal
exercise.
7. Access to the outbuilding is pedestrian only and can be gained via a side gate
and by walking through the garden to the outbuilding. The appeal property is
located within a relatively quiet residential estate with unrestricted roadside
parking available close by.
8. The point in contention is whether the outbuilding would be provided for a
purpose incidental to the enjoyment of the dwellinghouse at No 5 or whether it
would amount to a material change of use of a property so that it is no longer a
single dwellinghouse. Whether something amounts to material change of use is
a matter of fact and degree in each case, to be assessed in the context of the
planning unit. For a use to be considered incidental to the enjoyment of a
dwellinghouse, it must be of a scale and nature that is incidental to the
reasonable enjoyment of the normal residential use of the buildings and land
which comprise the dwellinghouse and its curtilage. In this regard, the key
tests are reasonableness and whether the overall character of the dwelling
changes as a result of the non-residential use.
9. The studio is relatively small and contained pilates equipment at the time of my
site visit. It is the appellant’s evidence that classes last for just short of an
hour. This allows transition in-between clients. Classes are generally attended
on a one to one basis, although the size of the building is capable of
accommodating two clients simultaneously and has done so infrequently in the
past. Given the limited size of the outbuilding, I accept that it is likely to
preclude more than two clients being within the studio at any one time.
10. Pilates classes do not appear to be inherently noisy. Although some clients
would be likely to walk to access the classes, it is not likely to be the case for
all clients. Moreover, given the availability an off-street parking space within
the curtilage of the appeal site and an absence of any restrictions on parking
on-street, this would be likely to readily encourage access to the appeal site by
private motor vehicle.
11. I appreciate that there is little neighbour objection to the proposal and no
instances of nuisance have been drawn to my attention. However, on the
appellant’s evidence, the existing use of the outbuilding for pilates is presently
Appeal Decision APP/N1920/D/20/3255407
3
in the region of 9 people per week. It is the Council’s case that by reason of the
extent of the hours sought and the dual attendance of clients to each session,
there could be in the region of 68 visitors weekly. The future situation could
therefore be very different to that which is experienced at present.
12. There is dispute between the main parties concerning the number of visitors to
the appeal site as a consequence of the proposal. On the basis of the hours
stated within the application, if planning permission were to be granted it would
allow use of the studio for pilates classes between the hours of 9am to 5pm
each Monday and Friday, 9am to 3pm every Tuesday, Wednesday and
Thursday, and 6pm to 8pm every Tuesday evening. Although there are few
classes proposed during evening hours, the hours of operation would be for a
significant part of the day during a large part of the working week. The
business would be capable of operating all year round.
13. Although the appellant suggests only a ‘modest desire to grow the business’
and that the number of visitors would be greatly reduced from the ‘worst case’
scenario envisaged by the Council, I am mindful this position could change over
time. On the basis of the proposed business hours and dual occupancy of
classes, the proposal would be capable of allowing some 68 visitors over the
course of a week.
14. Whilst the introduction of the outbuilding has not brought about a significant
change in the external character of the property, I find that there would be a
marked rise in people calling at the property and vehicular traffic over each
week and potentially for the entire year. The degree of disturbance would be
worsened by reason of the short period of transition between clients and the
attendance of multiple clients at any one time. In my view, this would result in
the scale of the business exceeding what might be expected at a family
dwelling of this size. Consequently, the business is of a kind that could not
operate from a residential property on an ancillary basis without there being a
significant adverse impact on the character and appearance of the surrounding
area.
15. I have had regard to the appellant’s willingness to reduce the operating hours
and/or the number of visitors to each class. Reference has been made to
limiting the occupancy of each class to a maximum of two persons and a daily
limit of five classes. However, even when taken in combination, the scheme
would be capable of generating in the region 10 visitors per day. To my mind,
this would not be sufficient to reduce the adverse harm I have described
above.
16. Reference has been drawn to comparisons with other home working uses
within a number of appeal decisions1. There is limited detail before me
concerning the site-specific circumstances of those developments.
Furthermore, the nature and scale of the ancillary uses of those schemes are
not directly comparable to the appeal proposal before me. For instance, I note
that the number of visitors to those schemes was found to range between ‘one
or 2 customers calling per week’2 to ‘an average of 6 clients per day (Thursday,
Friday, Saturday)’3. The appeal at Egerton Road4 concerned a
2 APP/D0121/C/19/3225137
3 APP/G2245/C/18/3215848 & 3207591
4 APP/J0350/W/18/3209360
Appeal Decision APP/N1920/D/20/3255407
4
workshop/outbuilding/home office and made little reference to persons calling
at the property. In the Woodfield Rise appeal5, despite the number of attendees
for each session being greater than the number proposed within the appeal
scheme, the total number of sessions over the course of a week was limited.
By reason of the differences between those schemes and the appeal proposal,
a comparison is of limited relevance in this instance and I have considered the
appeal before me on its individual planning merits.
17. Therefore, the use of the outbuilding as a pilates studio would conflict with
Policy CS8 of the Hertsmere Core Strategy (January 2013)(CS) and Policy
SADM30 of the Hertsmere Local Plan Site Allocations Development
Management Policies Plan (November 2016)(SADM) insofar as these policies
are supportive of development proposals in appropriate locations, recognise
and complement the particular local character of the area in which it is located
and is of high quality that is appropriate in scale, appearance and function to
the local context.
18. The Council’s reasons for refusal also cite a conflict with CS Policy CS9 and
SADM Policy SADM42. These policies are concerned with the appropriateness of
development proposals within Local Significant Employment Sites and town and
district centres. It has not been put to me by the Council that the appeal sites
falls within any of these locations and as such, I do not find that there would be
conflict with these policies. Nonetheless, this does not affect my findings with
regards to the conflict I have found with other policies of the development plan.
Living conditions
19. By reason of the close-knit arrangement of dwellings and their modest sized
rear garden areas, their private amenity areas would be highly sensitive to
noise arising from the comings and goings of individuals arriving and leaving
the appeal property. Taking into account that the business would operate for a
significant part of the and day during a large part of the working week and
given the relative peacefulness of these areas, the noise and disturbance
arising from the proposed scheme would be harmful to the living conditions of
neighbouring occupiers and materially compromise their living conditions.
20. Accordingly, I find that the living conditions of neighbouring occupiers would be
unduly compromised by reason of noise and disturbance. The proposal would
fail to accord with CS Policies SP1 and CS16 and SADM Policy SADM30 insofar
as these policies seek to ensure a healthy living environment where pollutants
such as noise are minimised and a high quality design that has limited impact
on, among other things, the amenity of neighbours with regard to nuisance. It
would also conflict with the aims of the Framework which, among other things,
seeks to create places which promote health and well-being with a high
standard of amenity for future users.
Other Matters
21. I have had regard to the evidence concerning the operation of the air-
conditioning unit. This supports the appellant’s case that there would be no
adverse harm arising from its usage. Additionally, given that the majority of
hours of operation are during daylight hours, I am not satisfied that the use of
lighting within the rear garden would be of a scale that would be unduly
5 APP/N1920/W/19/3221875
Appeal Decision APP/N1920/D/20/3255407
5
harmful. However, the absence of harm is a neutral matter that weighs neither
for nor against a proposal.
22. I am not satisfied that the absence of an express reference to ‘homeworking’
within the development plan engages the tilted balance. Other policies within
the development plan adequately provide for a consideration of the scheme’s
benefits and disbenefits. I recognise that home working would enable the
appellant to work flexibly and care for a young family, however, these are
personal benefits that seldom outweigh general planning considerations.
Although working from home would deliver some environmental benefit in
terms of the appellant avoiding the need to travel for work purposes, any
benefit is reduced given that clients would be likely to use a private motor
vehicle to access the appeal site.
23. I have had regard to a letter in support of the proposal. As the proposal would
achieve improvements to the physical health and mental well-being of those
individuals utilising the classes provided, this would be a modest benefit
weighing in favour of the proposal.
24. Reference has been made to the current Covid-19 situation and a move to
online classes thus reducing the number of in-person visits to the appeal site.
Whilst this may be the situation at present there is nothing before me to
demonstrate that there will not be a return to physical classes at a future date.
Conclusion
25. For the reasons given above, the appeal is dismissed.
E Brownless
INSPECTOR
£
Costs decision section
Costs Decision
Site visit made on 9 November 2020
by E Brownless BA (Hons) Solicitor (non-practising)
an Inspector appointed by the Secretary of State
Decision date: Wednesday, 17 March 2021
Costs application in relation to Appeal Ref: APP/N1920/D/20/3255407
5 Field View Road, Potters Bar EN6 2LY
• The application is made under the Town and Country Planning Act 1990, sections 78,
322 and Schedule 6, and the Local Government Act 1972, section 250(5).
• The application is made by Abbey Hope-Evans for a full award of costs against
Hertsmere Borough Council.
• The appeal was against the refusal of planning permission for ‘retrospective
construction and use of an outbuilding for a home business ancillary to the use of the
dwellinghouse’.
Decision
1. The application for an award of costs is refused.
Reasons
2. The Planning Practice Guidance advises that costs may be awarded against a
party who has behaved unreasonably and thereby caused the party applying
for costs to incur unnecessary or wasted expense in the appeal process.
3. The application for costs is in two parts. Firstly, in relation to procedural
matters, the Applicant cites a lack of cooperation on the Respondent’s part to
engage with the Applicant. Secondly, with regards to substantive matters, it is
the Applicant’s case that the Respondent was vague, generalised and
inaccurate in its decision-making process. Moreover, that it failed to properly
scrutinise the submission in light of similar cases and a previous appeal
decision. The appellant concludes that the appeal could have been avoided had
the Respondent sought to work proactively with the Applicant and examined
the use of suitable conditions that would have enabled the proposal to go
ahead.
4. I have had regard to the background provided by the Applicant. However,
matters relating to the choice of procedure regarding previous applications and
a decision by the Respondent to refuse the waiver of planning fees are not
matters for me to determine as part of this application.
5. There is clear dispute between the parties as to whether the Respondent
refused to engage meaningfully with the Applicant. In reaching a decision it is
clear to me that the Respondent had regard to the Applicant’s suggested
restriction on dual occupancy of classes. This formed part of the Respondent’s
assessment in terms of the maximum number of visitors to the appeal property
each week. Although it is not clear to me that the Respondent gave
consideration to a daily restriction on the number of classes, I have given
consideration to this matter myself and I have found that such a restriction
would not overcome the harm I have found.
Costs Decision APP/N1920/D/20/3255407
2
6. As part of the appeal process, further alternative operating arrangements have
been put forward by the appellant. These include individual attendance at each
class, reduced hours of operation on a Friday, no hours of operation on a
Friday, a maximum of 5 clients per day or 15 clients per week. It is not clear
on the information before me that these matters formed part of the original
application. The Applicant suggests that matters ‘were left deliberately open
ended’. The Respondent disagrees. Given these conflicting views and based on
the evidence before me I am unable to reach a conclusive view on this matter.
7. I note that the Officer Report failed to reference the Applicants email of the 5
May 2020 and referred to third party correspondence as an objection rather
than a comment. In addition, I have determined that there was no conflict with
a number of policies referred to by the Respondent in their reasons for refusal.
Whilst I appreciate the Applicant’s frustration regarding these matters, I am
not satisfied that these clearly demonstrate unreasonable behaviour nor that it
led to unnecessary or wasted expense in the appeal process. I note that the
Respondent actioned requests to provide copies of third party comments in a
timely manner. Furthermore, given the broad similarities between the appeal
scheme and the previous application1, I do not find it unreasonable that
content from the earlier Officer’s report was repeated in this instance.
8. My attention has been drawn to a letter in support of the application. However,
there is little evidence before me to substantiate the claim that the Respondent
failed to take it into account. Moreover, the exhibit2 shows a date of submission
as the 29 June 2020, whereas the application was determined by the
Respondent at an earlier date. Therefore, I cannot be certain when the letter of
support was submitted, the nature of the complaint nor its outcome. As such, I
am unable to conclude that the Respondent has failed to accurately portray
local consultation responses.
9. Furthermore, I am not satisfied that the Applicant has demonstrated a failure
on the Respondent’s part to have regard to previous appeal decisions and deal
with matters in a consistent manner. I have had regard to these matters in
reaching my decision and in a similar manner, I have found those schemes not
to be directly comparable to the appeal proposal.
10. Accordingly, I do not find that the Council have acted unreasonably. As such, I
conclude that unreasonable behaviour resulting in unnecessary or wasted
expense, as described in the Planning Practice Guidance, has not been
demonstrated. An award of costs is therefore not justified.
E Brownless
INSPECTOR
1 Planning Reference 19/1046/FUL
2 Appendix 5 to the Applicant’s Application for an aware of appeal costs
Expert Representation
Don't leave your appeal to chance.
Inspectors are inconsistent. We build a technical defense using precedents from our 182,000+ case archive.
No win, no fee Householder representation — you only pay if you win.