Erection of 2 dormer extensions on the front elevation and one dormer extension on the rear elevation. Replacing all existing glazing with high performance triple-glazed UPVC frame windows, and the installation of 2 glazed roof lights to rear dormer
📊
See the success rate & inspector analytics
Free to view — just create an account, no payment needed.
Sign Up FreeTechnical Issues Heatmap
Extensions
Heritage & Conservation
Policy Weight
Inspector’s Reasoning
Appeal Decision
Site visit made on 11th September 2017
by Alison Roland BSc DipTP MRTPI
an Inspector appointed by the Secretary of State for Communities and Local Government
Decision date: 27 September 2017
Appeal Ref: APP/E5900/D/17/3179030
36 Blondin Street, London, E3 2TR.
The appeal is made under section 78 of the Town and Country Planning Act 1990
against a refusal to grant planning permission.
The appeal is made by Mr Winston Raggatt against the decision of the Council of the
London Borough of Tower Hamlets.
The application Ref: PA/17/00484 dated 20 February 2017, was refused by notice dated
27 April 2017.
The development proposed is the erection of 2 dormer extensions on the front elevation
and one dormer extension on the rear elevation. Replacing all existing glazing with high
performance triple-glazed UPVC frame windows, and the installation of 2 glazed roof
lights to rear dormer.
Procedural Matter
1. The description cited in the header above replicates that cited on the planning
application form. During the course of the application the proposal was
amended to rooflights on the front elevation, dormer to rear roof slope and
installation of triple glazed UPVC frame windows and I shall determine the
appeal accordingly.
Decision
2. The appeal is dismissed insofar as it relates to the dormer to the rear roof
slope. The appeal is allowed insofar as it relates to rooflights on the front
elevation and installation of triple glazed UPVC frame windows and planning
permission is granted for the same, at 36 Blondin Street, London, E3 2TR, in
accordance with the terms of the application Ref: PA/17/00484, dated 20
February 2017 and the plans submitted with it (so far as relevant to that part of
the development hereby permitted) and subject to the following conditions:
1) The development hereby permitted shall begin not later than three years
from the date of this decision.
2) The development hereby permitted shall be carried out in accordance
with the following approved plans: 214-100 - Site Location Plan; 214-110
- Existing Lower Ground Floor Plan; 214-111 - Existing Ground Floor
Plan; 214-112 - Existing First Floor Plan; 214-113 - Existing Second
Floor Plan; 214-114 - Existing Roof Plan; 214-120 - Existing Front And
Rear Elevation; 214-130 - Existing Section A-A; 214-131 - Existing
Section B-B; 214-201 A - Proposed Ground Floor Plan; 214-202 A -
Appeal Decision APP/E5900/D/17/3179030
2
Proposed First Floor Plan; 214-203 B - Proposed Second Floor Plan;
214-204 C - Proposed Loft Plan; 214-206 C - Proposed Roof Plan; 214-
220 C - Proposed Front And Rear Elevation; 214-230 A - Proposed
Section A-A ; 214-231 C - Proposed Section B-B; 214-232 B - Proposed
Section C-C; 214-200 A - Proposed Lower Ground Floor Plan.
Main Issue
3. The main issue in this appeal is whether the proposal would preserve or
enhance the character or appearance of the Fairfield Road Conservation Area
(CA).
Reasons
4. The CA is defined by its mixed character, with a strongly industrial feel
bordering the railway and a more typically residential character to the South,
East of Fairfield Road. The Fairfield Road Conservation Area Character Appraisal
and Management Guidelines draw attention to the fact that the northern part of
the CA is dominated by a substantial former mill complex, the Bryant and May
Match Works Factory which is Grade II Listed. Blondin Street lies to the North
and is comprised substantially of modern terraced housing and flats with a
smaller group of older terraces at its eastern end.
5. The appeal property stands in the midst of a terrace which has an
uncompromisingly modern design and materials palette. The properties across
the opposite side of the road whilst of differing design, are also modern and
feature extensive use of metalwork to balconies, as well as unusual flat roofed
metal entrance porches.
6. In this context of contemporary properties, the proposed front roof lights would
not look out of place. The larger of the two would broadly align with the full
height glazed strip which stands to one side of the entrance door and whilst the
smaller one would not directly align with the windows beneath, the degree of
asymmetry would be minimal and insufficient to draw the eye. They would to
my mind amount to an unremarkable addition to this contemporary property
and sited on this elevated roof slope in a street with a strong sense of enclosure
to either side, would not be prominent viewed from the public domain, although
they would be clearly visible from the properties opposite.
7. However, I take a different view in relation to the proposed rear dormer. Whilst
I take the appellant’s point that its lead cladding and asymmetric glass splinter
render it of more interest than a typical box dormer, the fact is that it would
introduce a significant degree of built form onto a roof which is otherwise devoid
of such structures. It would thus appear as an oddity in the wide unbroken
expanse of roof scape which characterise this and the adjoining terraced block.
Whatever view one takes about the aesthetic merits of these blocks, the fact is
that other than a modest solar installation on the adjoining property, they do
not feature roof additions and have a very consistent appearance.
8. Whilst I did see some dormers on properties at the Western end of Blondin
Street visible from Menai Place and a mansard type addition to the property at
the junction of Blondin Street with Fairfield Road, there is a greater diversity in
house types at that particular location and the properties do not share the same
consistency in style as the appeal site. The context is thus not comparable.
Appeal Decision APP/E5900/D/17/3179030
3
9. I also accept that the rear of the appeal site is effectively a private gated area
and not open to the public. Nonetheless, from the number of parked cars
thereon, it is clearly frequented by a large number of people and the proposed
dormer would be particularly strident when viewed from the upper floors of the
buildings to the South East.
10.The rear dormer would thus introduce an obtrusive addition to the rear roof
which would fail to satisfactorily integrate with the host property and wider
terrace of which it forms part. This element of the proposal would thus fail to
preserve or enhance the character or appearance of the CA. This would bring it
into conflict with the objectives of the National Planning Policy Framework,
Policies 7.6 and 7.8 of the London Plan (2016), Policy SP10 of the Tower
Hamlets Core Strategy Development Plan Document 2025 (2010) and Policies
DM24 and DM27 of the Tower Hamlets Local Plan Managing Development
Document Development Plan Document (2013). These seek to secure high
quality design which is sensitive to and enhances the local character and setting
of the development and protects and enhances the significance of heritage
assets such as conservation areas. I appreciate the proposal would enhance the
accommodation at this property, but nonetheless consider the harm identified
would outweigh any benefit in this regard.
11.The Council take no exception to the proposed triple glazing and I have no
reason to either. In addition, despite my conclusions in relation to the rear
dormer, I have found that the proposed front roof lights would amount to a
minor and inconsequential addition to the property. As these elements of the
proposal are clearly divisible from the remainder, I shall issue a split decision
dismissing the appeal in relation to the dormer, but allowing the balance of the
development.
12.In addition to the standard time limit for commencement of development, a
condition confining the approval to specified plans is necessary for certainty.
The Council also suggest a matching materials condition, which is inappropriate
due to the materials specified.
ALISON ROLAND
INSPECTOR
Expert Representation
Don't leave your appeal to chance.
Inspectors are inconsistent. We build a technical defense using precedents from our 182,000+ case archive.
No win, no fee Householder representation — you only pay if you win.