Appeal Decision
Site visit made on 23 November 2016
by G Powys Jones MSc FRTPI
an Inspector appointed by the Secretary of State for Communities and Local Government
Decision date: 07 December 2016
Appeal Ref: APP/T3725/D/16/3158488
24 Freeman’s Close, Leamington Spa, Warwickshire, CV32 6EZ
The appeal is made under section 78 of the Town and Country Planning Act 1990
against a refusal to grant planning permission.
The appeal is made by Mr & Mrs Jason Ventress against the decision of Warwick District
Council.
The application Ref W/16/0669, dated 12 April 2016, was refused by notice dated
11 July 2016.
The development proposed is the erection of a two-storey side extension, single storey
front extension and rear dormer window.
Decision
1. The appeal is allowed and planning permission is granted for the erection of a
two-storey side extension, single storey front extension and rear dormer
window at 24 Freeman’s Close, Leamington Spa, Warwickshire, CV32 6EZ in
accordance with the terms of the application Ref W/16/0669, dated 12 April
2016, subject to the conditions set out in the attached Schedule.
Preliminary matter
2. In the interests of brevity the Council’s description of the proposed
development used in its decision notice has been utilised. It is more succinct
than that in the application form, but is nevertheless accurate.
Main issues
3. The main issue is the effect of the proposals on the character and appearance
of the host property and its surroundings.
Reasons
4. The appeal property is one of several detached properties set at the end of a
residential cul-de-sac of relatively modern construction. The appellant
proposes a two-storey extension to replace the existing garage; this would
display a front gable feature.
5. A rear dormer, front rooflights and a single storey front extension are also
proposed, to which the Council does not object. I have no reason to object to
these features either.
6. The appellant considers the design and scale of his proposals, as they affect
the front elevation, would be similar to that carried out at No. 25, the next-
door property.
Appeal Decisions APP/T3725/D/16/3158488
2
7. The Council’s concerns, having regard to advice contained in its Residential
Design Guide – Supplementary Planning Guidance (SPG), is that the ridge of
the proposed side extension would not be set down from that of the host
property and that the gable would dominate the front elevation. In
combination, these features would not therefore, in the Council’s view, prove
subordinate to the scale of the host property and would appear incongruous in
the street scene.
8. The Council does not regard the works carried out to No 25 to be a justification
for the current proposal since planning permission was granted for these works
prior to the adoption of its SPG.
9. The alteration carried out to No 25’s front elevation would not, in itself, justify
granting planning permission here, but it cannot be ignored or discounted since
it contributes to forming local character. Moreover, irrespective of the advice
referred to in the SPG, the works carried out to No 25 look perfectly acceptable
to the eye in terms of scale and appearance, and the general effect on the
street scene.
10. It follows, in my opinion, that the works proposed to the front of the appeal
property would not look out of place or incongruous, as suggested by the
Council. The property is well separated from its neighbours on either side, and
the scale of the proposals and their design would prove appropriate in their
spatial and visual contexts.
11. The appeal property is visually sheltered, being tucked away at the end of the
cul-de-sac. It can barely be seen from the entrance to the street. The
proposals, if built, would go almost unnoticed, and the visual impact of the
proposal on its surroundings would be minimal and entirely acceptable. This,
in my view, is a situation where the precise advice of the SPG, referred to by
the Council, need not be slavishly followed.
12. I conclude that the proposed development could be built without harming the
character and appearance of the host property or its surroundings its
surroundings. Accordingly, no conflict arises with those provisions of policy
DP1 of the Warwick District Local Plan (DLP) directed to ensure that new
development is well designed and respects local character.
Conditions
13. The Council’s suggested condition relating to materials shall be imposed in the
interests of visual amenity.
14. It is also necessary in the interests of certainty that the development is built in
accordance with the approved plans, and a condition to this effect is imposed.
15. So as to comply with the provisions of DLP policy DC13 and in the interests of
sustainability, the Council’s condition relating to energy efficiency is imposed.
16. The Council’s suggested other additional conditions are designed to protect
neighbouring living conditions from adverse effects with particular reference to
noise nuisance and privacy. Their suggested conditions in this respect are
therefore imposed to protect neighbouring residential amenity, albeit in a
slightly modified form.
Appeal Decisions APP/T3725/D/16/3158488
3
Other matters
17. Reference has been made to other development plan policies but those to
which I have referred are considered the most relevant in the particular
circumstances of this case.
18. All other matters raised in the representations have been taken into account,
including the views of the Town Council, which offered no objection. No other
matter is of such strength or significance as to outweigh the considerations that
led me to my conclusions.
G Powys Jones
INSPECTOR
Schedule of Conditions
1. The development hereby permitted shall begin not later than three years
from the date of this decision.
2. The materials to be used in the construction of the external surfaces of the
development hereby permitted shall match those used in the existing
building.
3. The development hereby permitted shall be carried out in accordance with
the following approved plans: Drawing Nos. 14/03-01; -02; -03 & -04.
4. The development hereby permitted shall not be commenced unless and until
a scheme showing how either a) at least 10% of the predicted energy
requirement of the development will be produced on or near to the site from
renewable energy resources, or b) a scheme showing how at least 10% of
the energy demand of the development and its CO² emissions would be
reduced through the initial construction methods and materials has been
submitted to and approved in writing by the Local Planning Authority. The
development shall not be first occupied until all the works within the
approved scheme have been completed and thereafter the works shall be
retained at all times and shall be maintained strictly in accordance with
manufacturer’s specifications.
5. If an air source heat pump is chosen as the method to comply with the
requirement for renewable energy, noise arising from the air source heat
pump(s) permitted, when measured one metre from the facade of any noise
sensitive premises, shall not exceed the background noise level by more
than 3dB (A) measured as LAeq (5 minutes). If the noise in question
involves sounds containing a distinguishable, discrete, continuous tone
(whine, screech, hiss, hum etc.) or if there are discrete impulses (bangs,
clicks, clatters, thumps etc.) or if the noise is irregular enough to attract
attention, 5dB(A) shall be added to the measured level.
6. Prior to the occupation of the development hereby permitted, the first floor
side-facing window in the south-west elevation shall be permanently glazed
with obscured glass and shall be non-opening unless the parts of the
window that can be opened are more than 1.7 metres above the floor of the
room in which the window is installed. The obscurely glazed window shall be
retained in that condition at all times.
Appeal Decisions APP/T3725/D/16/3158488
4
Expert Representation
Don't leave your appeal to chance.
Inspectors are inconsistent. We build a technical defense using precedents from our 182,000+ case archive.
No win, no fee Householder representation — you only pay if you win.